S.No |
Project Title |
Contract No |
Client |
Location |
End Date |
Scope |
01 |
ITC Civil works for DUBA GREEN ISCC POWER PLANT |
|
SEC / BMB |
Jeddah |
June 2019 |
![Construction of ITC infrastructure including construction of communication duct banks, supply and and install Hand holes and various types of manholes, install sub duct, nylon rope, hand hole/ manhole accessories, copper cable anf fiber optic cable, splicing termination and testing etc complete.](_Image/scope.png) |
02 |
Reinforcement of Makkah & Madinah Fiber Optic Network. |
4400003959 |
Saudi Electricity Company |
Makkah & Madinah |
December, 2017 |
|
03 |
Telecom Room Expansion in Various Sites in COA, (Duct Bank System for Communication System) |
4400006940/00 |
Baud Telecom Company (BTC) |
Various Sites in-COA |
May 2017 |
![Scope: Supply & Installation of Optical Fiber Cable Single mode 96 cores including excavation and backfilling in Soft Soil with Duct Trench 450mm width and 600 mm depth for 2 way for 110mm PVC complete with plastic rope & warning tape & Shelter Foundation with Shelter Fixation, Testing & Survey, Engineering and design etc.](_Image/scope.png) |
04 |
OSP Cable Construction & Restoration |
4400003029 |
Saudi Electricity Company |
Kingdom Wide |
15-03-2017 |
![Scope: Installation of Outside/Inside Plant Telephone Cabling System, Premise Distribution System, Copper and Fiber-Optic Cables, Manholes and Conduit System, and other accessories at various SEC locations in the Kingdom of Saudi Arabia.](_Image/scope.png) |
05 |
Proposed F.O. Cable Links between Various Sub-Stations in COA. |
4400004452 |
GIZA Arabia |
Various Sites in-COA |
May, 2016 |
|
06 |
OSP/ISP/PDS System for Rabigh PP (RGB IPP-2) 20134018-WFO-022-08-PDS |
|
Hyundai Heavy Industries Co. Ltd. |
Rabigh |
March, 2016 |
|
07 |
Splicing and Testing of Leasbale FO links Kingdm Wide |
3000014970 |
Saudi Electricity Company |
Kingdom Wide |
June, 2014 |
|
08 |
OSP/ISP/PDS works in Jeddah South Power Plant. |
20134018-WFO- 022-01 |
Hyundai Heavy Industries Co. Ltd. |
Jeddah |
May, 2014 |
|
09 |
380Kv DC Transmission Line Qurrayat PP to Future Tabarjal BSP |
31031138 |
Al-Shareef group and KEC Ltd. |
Qurrayat PP to Future Tabarjal BSP |
March, 2014 |
|
10 |
Installation of ITC OSP cables to fuel unloading area in WOA |
|
Saudi Electricity Company |
TABUK, AL WAJH, SHOAIBA |
December, 2013 |
|
11 |
OPGW/UGNMFOC Splicing & Testing Works-J1081 at Jizan |
|
M/s AUVA Projects & Supplies Co. |
Jizan |
December, 2013 |
|
12 |
Underground Fiber Optic Cable Link in (FOA) Phase-I between Al-Jouf to Sadea. |
31031138 |
Al-Shareef group and KEC Ltd. |
Al-Jouf to Sadea |
June, 2013 |
|
13 |
Civil works for GCC Ministries connectivity project |
|
Saudi Ericsson |
Riyadh |
April, 2013 |
|
14 |
Relocation of Qassim-Madinah UG FOC From National Guard Land in Madinah |
4400000714 |
Saudi Electricity Company |
Qassim-Madinah |
Sep, 2013 |
|
16 |
Long Haul fiber optic cable link between Mouyah and Ushairah. |
4400000649 |
Saudi Electricity Company |
Mouyah and Ushairah |
Sep, 2013 |
![Scope: Supply & Laying of FOC Cable in Mouyah-Ushairah (WOA) for a Distance of 144Km including Splicing, Terminate & Testing etc complete, supply & installation works.](_Image/scope.png) |
17 |
Upgrade of Network Fiber Optic Connectivity (FOC) |
GT110IT12 |
Khafji Joint Operation (KJO) |
Khafji |
Sep, 2013 |
![Scope: Upgrade of Network Fiber Optic Connectivity (FOC) between CCR, Automation, PMCR, HOOT, WTF, Power Plant, Emarra Khafji, Warehouse etc.](_Image/scope.png) |
18 |
Civil works for degraded F.O. cable routes of MODA F.O. cable network various parts of Kingdom |
|
Saudi Ericsson |
|
Sep, 2013 |
![Scope: Civil works for degraded F.O. cable routes of MODA F.O. cable network various parts of Kingdom](_Image/scope.png) |
19 |
Underground Fiber Optic Cable Network in(WOA) |
20831205/00 |
Saudi Electricity Company |
Tabuk, Dhuba, Khayber & Taimah |
Nov, 2013 |
![Scope: (475km) Supply & Laying of FOC Cable in Tabuk, Dhuba, Khayber & Taimah (WOA) for a Distance of 470Km including Splicing, Terminate & Testing etc complete, supply & installation telecom repeater shelters.](_Image/scope.png) |
20 |
Civil works for degraded F.O. cable routes of MODA F.O. cable network various parts of Kingdom |
20931090/00 |
Saudi Electricity Company |
Dhuba, Al-Wajh & Um-Luj |
June, 2012 |
![Scope: (330km) Supply & Laying of FOC Cable in Dhuba PP S/S, Al-Wajh PP S/S & Um-Luj S/S (WOA) for a Distance of 325Km including Splicing, Terminate & Testing etc complete, supply & installation telecom repeater shelters.](_Image/scope.png) |
21 |
Civil Work for FOC Installation on ABQAIQ-AHSA Road |
|
Saudi Ericsson |
ABQAIQ-AHSA Road |
Dec, 2012 |
![Scope: Civil Work for FOC Installation on ABQAIQ-AHSA Road](_Image/scope.png) |
22 |
Supply and Installation of Flexible Marker Posts |
|
Saudi Ericsson |
Riyadh |
Dec, 2012 |
![Scope: Supply and Installation of Flexible Marker Posts](_Image/scope.png) |
23 |
Supply & Installation of 24 Fiber G652D Cable & 50x2x0.90 CEFE Copper Cable in Majma. |
|
Saudi Ericsson |
Majma |
Dec, 2012 |
![Scope: Supply & Installation of 24 Fiber G652D Cable & 50x2x0.90 CEFE Copper Cable in Majma.](_Image/scope.png) |
24 |
RSADF Fiber Opitcal Cable Work at Dawadmi, Nisah, Rania & Solail |
10/29 |
Saudi Bell Group |
Dawadmi, Nisah, Rania & Solail |
March, 2010 |
![Scope: Design & Engineering of FOC laying of FOC Installation Splicing, Testing Commissioning, Laying of Copper Cables, Placing of MH's/HH's, PVC duct jointing, Testing & Commissioning.](_Image/scope.png) |
25 |
STC-Yanbu/Taif |
2051309 |
STC |
Yanbu/Taif |
March, 2010 |
![Scope: Design & Engineering of FOC laying of FOC Installation MSAN Cabinets, Splicing, Testing Commissioning, Laying of Copper Cables, Placing of MH's/HH's, PE duct jointing, Testing & Commissioning.](_Image/scope.png) |
26 |
STC-Yanbu/Taif |
110002 |
STC |
Yanbu/Taif |
March, 2010 |
![Scope: Design & Engineering of FOC laying of FOC Installation MSAN Cabinets, Splicing, Testing Commissioning, Laying of Copper Cables, Placing of MH's/HH's, PE duct jointing, Testing & Commissioning.](_Image/scope.png) |
27 |
Splicing and testing of OPGW |
|
M/s Raissy HGPT |
Madina |
May, 2010 |
![Scope: Splicing and testing of OPGW, Installation of splitter box, Termination, End to End testing, etc](_Image/scope.png) |
28 |
Fiber Opitcal Cable Work at Abha |
|
Modern Building |
Abha |
May, 2010 |
![Scope: Supply and Installation of data cabinet, F.O patch panel, Pre & post installation testing, splicing , Termination, etc](_Image/scope.png) |
29 |
Underground Fiber Optic Cable Link Qassim-Medinah |
10531176/00 |
Saudi Electricity Company |
Al-Qassim-Medinah |
14-07-2010 |
![Scope: Laying of FOC Cable from Al-Qassim Power Plant to Medina Munawarah for a Distance of 500Km including Telecom Repeater Shelters Splicing, Terminate & Testing.](_Image/scope.png) |
30 |
Installation FOC SM 12F from Station Jabl-Al-Sahin to Site 309 (MODA) |
|
Saudi Ericsson |
Khamis-Mushayat |
Jun,2010 |
![Scope: Installation FOC SM 12F from Station Jabl-Al-Sahin to Site 309 for a Distance of 1400m.](_Image/scope.png) |
31 |
Underground Fiber Optic Cable Link between Ruwaydah 8605 S/S (COA)-Al-Muwyah 110/33kV S/S (WOA) |
10631150/00 |
Saudi Electricity Company |
Ruwaydah - Al Muwyah |
Nov,2010 |
![Scope: Supply & Laying of FOC Cable from Ruwaydah 8605 S/S (COA)-Al Muwyah 110/33KV S/S (WOA) for a Distance of 360Km including Splicing, Terminate & Testing.](_Image/scope.png) |
32 |
STC-Taif |
2045864 |
STC |
Taif |
Jan, 2009 |
![Scope: Design & Engineering of FOC laying of FOC Installation MSAN Cabinets, Splicing, Testing Commissioning, Laying of Copper Cables, Placing of MH's/HH's, PE duct jointing, Testing & Commissioning.](_Image/scope.png) |
33 |
STC-Yanbu/Taif/Jizan |
2050274 |
STC |
Yanbu, Taif and Jizan |
July, 2009 |
![Scope: Design & Engineering of FOC laying of FOC Installation MSAN Cabinets, Splicing, Testing Commissioning, Laying of Copper Cables, Placing of MH's/HH's, PE duct jointing, Testing & Commissioning.](_Image/scope.png) |
34 |
OSP/PDS upgrading of Cabling System West Operating Area |
20561101/00 |
Saudi Electricity Company |
Different Location of Western Operating Area |
Dec, 2008 |
![Scope: Installation of Outside/Inside plant telephone & F.O Cable, PDS System Local Area Network (PDS-LAN) & its associated equipment.](_Image/scope.png) |
35 |
STC |
2032512 |
STC |
Jizan, Taif, Al-Baha and yanbu |
April, 2008 |
![Scope: Design & Engineering of FOC laying of FOC Installation MSAN Cabinets, Splicing, Testing Commissioning, Laying of Copper Cables, Placing of MH's/HH's, PE duct jointing, Testing & Commissioning.](_Image/scope.png) |
36 |
FIBER OPTIC CABLE CONNECTIVITY BETWEEN GATHERING STATION AND ALL FLOW STATIONS ( Y1, Y2, Y3, Y4 ) |
BT649IT07 |
Khafji Joint Operation (KJO) |
Khafji (Offshore) |
Jan, 2008 |
![Scope: FIBER OPTIC CABLE CONNECTIVITY BETWEEN GATHERING STATION AND ALL FLOW STATIONS ( Y1, Y2, Y3, Y4 )](_Image/scope.png) |
37 |
Patriot battalion to C3 network link RSADF, Khamis |
|
RSADF |
Khamis, Mushayat |
July, 2007 |
![Scope: Site Survey Engineering & Design. Installation of D/B F.O.C of 16 & 8 Core SM in between different air bases on LSTK-project.](_Image/scope.png) |
38 |
STC Jizan & Taif |
2022670 |
STC |
Jizan - Taif |
|
![Scope: Design & Engineering of FOC laying of FOC Installation MSAN Cabinets, Splicing, Testing Commissioning, Laying of Copper Cables, Placing of MH's/HH's, PE duct jointing, Testing & Commissioning.](_Image/scope.png) |
39 |
OSP / PDS Cabling System at 4th Operating Area |
30331021/00 |
Saudi Electricity Company |
4th Operating Area |
Jun, 2006 |
![Scope: This project provides Survey, Design & Installation of Outside / Inside Plant Telephone and Fiber Optic Cables & its associated Hand holes / Manholes and conduit system, Terminal Blocks, Joint Boxes, Protectors, Splices, Racking, Hardware and Grounding system. This new cable Installation is required at several Power Plant, Local offices, and Work Centers to replace old and deteriorating Cables and or to increase the existing capacity. New cable route are also required to provide access to existing or proposed Fiber Optic / Carrier Systems. This Contract is LSTK Basis.](_Image/scope.png) |
40 |
MODA Frequency Replacement Project, LDN-FON Route Najran - Sultana |
|
Saudi Telecom Co. |
Najran-Fahad-Arisa-Sultana-Husainiyah |
Oct, 2005 |
![Scope: (208.6km) A complete LDN project surveyed, planned, designed and in progress of implementation. It includes Cable installation by mole plough, Cable installation in Duct, Splicing, Termination of Cable in ODF and many related activity to various STC Exchanges, GSM, WLL.](_Image/scope.png) |
41 |
Civil Works for OSP Network. Contract No. |
0215442 |
Saudi Telecom Co. |
Tabuk, Hafr Al-Batin, Abha, Al-Baha, Nijran |
|
![Scope: Laying of FO Cable Network of cable, connecting various Exch. with RAN, Axis of Saudi Electricity Co. till RAN, including all types of Civil works, Inst. of Electronic Cabinets, Laying of Sub-duct & mini-duct, Splicing, Testing & Termination, Installation of ODF, etc. complete](_Image/scope.png) |
42 |
OPGW Work |
SEC-CRB 38/20/21 |
Kadi Trad. & Cont. |
Qassim |
April, 2005 |
![Scope:Drum Testing, Splicing, Termination, Testing, Documentation & Commissioning.](_Image/scope.png) |
43 |
OPGW Work |
SEC-CRB 504/22/3 |
Rajab & Silsilah / L.G / SST |
Howta Suddair |
|
![Scope: Drum Testing, Splicing, Termination, Testing, Documentation & Commissioning.](_Image/scope.png) |
44 |
OPGW Work |
SEC-CRB 523/22/3 |
Rajab & Silsilah / L.G / SST |
Hail |
16-02-2004 |
![Scope: Drum Testing, Splicing, Termination, Testing, Documentation & Commissioning, successfully completed and handed over to SEC-CRB in presence of SEC-Representatives, LG & SST Representatives for Commissioning.](_Image/scope.png) |
45 |
Diversion of working Fiber (OPGW-NFOC) for SEC-CRB |
SEC-CRB 513/20/3 |
ATECON |
Riyadh |
Nov, 2003 |
![Scope: Diversion of working Fiber (OPGW-NFOC) for SEC-CRB for SEC-CRB of S/s 808. Within the limit of shutdown time of SEC i.e. 2 hrs. with complete testing, Documentation & Commissioning.](_Image/scope.png) |
46 |
OSP Network 450-K |
|
STC |
Kingdom wide |
16-09-2003 |
![Scope: Excavation as per MOC & MOMRA requirements, Inst. of MHs / HHs, Construction of different ways of Ducts encased in Concrete, Mandrilling, Pulling cable (Copper & Fiber) in ducts and sub ducts, Inst. diff. types of Cross connection Cabinets, Pedestals with terminal blocks, Installation of different sizes of MDF & ODF in Exchanges, Inst. of MDF terminal blocks & termination of ODF. Including Splicing, Termination & Testing of Copper & Fiber cables with Documentation, preparation of As built Drawings, Commissioning, Preliminary Acceptance Test (PAT) & Handing over of Projects](_Image/scope.png) |
47 |
450k Project |
|
STC |
Taif |
20-07-2003 |
![Scope: (205km) Laying of FO Cable Network of cable size 96 & 36 Fiber, connecting various Exch. with RAN, including all types of Civil works, Inst. of Electronic Cabinets, Laying of Sub-duct & mini-duct, Splicing, Testing & Termination, Installation of ODF, etc. complete](_Image/scope.png) |
48 |
450k Project Hawi Exchange. |
34-565 |
STC |
Taif |
18-03-2003 |
![Scope: (11.22km) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
49 |
450k Project |
|
STC |
Taif |
10-03-2003 |
![Scope: (70km) Laying of FO Cable Network of cable size 96 & 36 Fiber, connecting various Exch. with RAN, including all types of Civil works, Inst. of Electronic Cabinets, Laying of Sub-duct & mini-duct, Splicing, Testing & Termination, Installation of ODF, etc. complete](_Image/scope.png) |
50 |
TEP-450K-DAKHNA ROAD |
|
STC |
Qassim |
23-02-2003 |
![Scope: (1km) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
51 |
TEP-450K -DAKHNA ABDALIYA |
|
STC |
Qassim |
10-02-2003 |
![Scope: (6km) Inst. of PVC duct & sub-ducts in a duct. Pull FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
52 |
TEP-450K- Al-JANDAL AR-RASS |
|
STC |
Qassim |
07-02-2003 |
![Scope: (205km) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
53 |
TEP-450K- Al-SANAIYA AR-RASS |
|
STC |
Qassim |
05-06-2002 |
![Scope: (205km) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
54 |
TEP-450K Al-MEHFAL |
|
STC |
Qassim |
06-05-2002 |
![Scope: (2km) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
55 |
TEP-450k |
1542141 |
STC |
Yanbu |
09-01-2002 |
![Scope: (46.94km) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
56 |
TEP-550K -SANAIYA (TIFS) |
4423833 |
STC |
Taif |
16-11-2001 |
![Scope: (1.2km) Inst. of 4Way 32mm sub duct, Instl. of FOC, splicing & Termination of cable in ODF.](_Image/scope.png) |
57 |
TEP Key Account |
1433-232 |
STC |
Jubail |
27-10-2001 |
![Scope: (6.5km) Installation of FOC from Musanidah Exchange to Royal Commission Bldg. & Jubail Industrial College & Petrochemicals Co.](_Image/scope.png) |
58 |
OSP Network 550-K |
|
STC |
Kingdom wide |
12-10-2001 |
![Scope: Excavation as per MOC & MOMRA requirements, Inst. of MHs / HHs, Construction of different ways of Ducts encased in Concrete, Mandrilling, Pulling cable (Copper & Fiber) in ducts and sub ducts, Inst. diff. types of Cross connection Cabinets, Pedestals with terminal blocks, Installation of different sizes of MDF & ODF in Exchanges, Inst. of MDF terminal blocks & termination of ODF. Including Splicing, Termination & Testing of Copper & Fiber cables with Documentation, preparation of As built Drawings, Commissioning, Preliminary Acceptance Test (PAT) & Handing over of Projects](_Image/scope.png) |
59 |
TEP-450K, |
|
STC |
Al-Baha |
08-10-2001 |
![Scope: (4.05km) Supp & Inst. of 4 standard sub ducts in main duct, Inst. FOC- Group (1-3) in sub duct, Inst. of handholes](_Image/scope.png) |
60 |
TEP-450K, |
|
STC |
Al-Baha |
04-10-2001 |
![Scope: (3.31km) Supp & Inst. of 4 standard sub ducts in main duct, Inst. FOC- Group (1-3) in sub duct, Inst. of handholes](_Image/scope.png) |
61 |
HALAQAH (TCEN) |
A122 /A078 |
STC |
Taif |
09-09-2001 |
![Scope: (4.01km) Inst. of 4Way 32mm sub duct, Instl. Of FOC, splicing & Termination of cable in ODF.](_Image/scope.png) |
62 |
TEP-450K, |
|
STC |
Al-Baha |
06-09-2001 |
![Scope: (2.63) Supp & Inst. of 4 standard sub ducts in main duct, Inst FOC- Group (1-3) in sub duct.](_Image/scope.png) |
63 |
TEP-550K, RAN 1/2/3 |
3427428 |
STC |
Jizan |
27-08-2001 |
![Scope: (24) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
64 |
SUHAILI (TIFS) |
A122 /A079 |
STC |
Taif |
10-08-2001 |
![Scope: (3.2km) Inst. of 4Way 32mm sub duct, Instl. Of FOC, splicing & Termination of cable in ODF.](_Image/scope.png) |
65 |
TEP-450K, |
3425529 |
STC |
Al-Baha |
07-08-2001 |
![Scope: (7.08) Supply & Inst. of 50mm polythelene pipe, Install FOC-Group (1-3) in 50mm Polythelene pipe](_Image/scope.png) |
66 |
TEP-450K, RAN 1/2/3 |
3427428 |
STC |
Jizan |
30-05-2001 |
![Scope: (3.27km) Supply & Inst. of 3 sub duct in empty sub duct](_Image/scope.png) |
67 |
TEP-550K (FON) – |
|
STC |
Jubail |
08-04-2001 |
![Scope:(32km) Operation of continuous well point system, Aramco pipeline crossing done manually. Thrust boring works at various locations. Pulling FO cable, jointing, termination, testing & commissioning.](_Image/scope.png) |
68 |
MODA Maintenance -Laying of new Direct Buried cable & removing the old cable. |
|
Saudi Ericsson |
Dilam |
04-09-2000 |
![Scope: Excavation for laying of new FO cable beside existing FO cable & removing old cable](_Image/scope.png) |
69 |
MODA Maintenance -Laying of new Direct Buried cable & removing the old cable. |
|
Saudi Ericsson |
Qatif |
20.07-2000 |
![Scope: <1.2km) Excavation for laying of new FO cable beside existing FO cable & removing old cable](_Image/scope.png) |
70 |
MODA Maintenance -Direct Buried FO cable |
|
Saudi Ericsson |
Artawiyah Camp |
14-06-2000 |
![Scope: 0.6km) Inst. of 2-way duct & Marker Post](_Image/scope.png) |
71 |
Eskan Village (Riyadh) OSP Network |
TKSP/625 |
Saudi Ericsson |
Eskan Village (Riyadh) |
25-04-2000 |
![Scope: (2.27km) Inst. of PVC duct & sub-ducts in a duct. Pulling FO cable in a sub-duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
72 |
STC Job – 7511183 |
7511183 |
Saudi Ericsson |
Riyadh |
30-08-1998 |
![Scope: FOC UMUX1100 & mini Link installation](_Image/scope.png) |
73 |
TEP-6-OSP, |
224047 |
STC |
Kingdom wide |
|
![Scope:](_Image/scope.png) |
74 |
TEP-6-OSP, (Junction) |
224041 |
STC |
Kingdom wide |
|
![Scope: Inst. of FO cable and copper cables, M/holes, H/holes Inst. of PVC duct & sub-ducts in a duct. Jointing, termination, testing & commissioning.](_Image/scope.png) |
75 |
MODA Maintenance-Khamis Airbase |
|
Saudi Ericsson |
Khamis Mushayat |
20-02-1998 |
![Scope: (5.3km) Laying of new Direct Buried cable & removing the old cable.](_Image/scope.png) |
76 |
MODA Maintenance-Taif Airbase - Laying of new Direct Buried cable & removing the old cable. |
|
Saudi Ericsson |
Taif |
06-02-1998 |
![Scope: (2.85km) MODA Maintenance-Taif Airbase - Laying of new Direct Buried cable & removing the old cable.](_Image/scope.png) |
77 |
Ministry of Defense & Aviation - Fiber Optic Cable Laying (Direct Buried) |
|
MODA |
(Dammam to Jubail, KKMC, Haf'r Al-Batin) |
23-08-1993 |
![Scope: (800km) Inst. of direct buried FO cable, including Thrust boring works, under Aramco pipeline / highway crossings, road bridge/wadi crossings at various locations in 800 kms. Length. Inst. of Manholes, Hand holes, with splicing, testing, and commissioning.](_Image/scope.png) |
78 |
Royal Saudi Air Force - Fiber Optic Cable Laying (Direct Buried) |
|
RSAF |
Eastern Region |
29-05-1991 |
![Scope: (180km) Inst. of direct buried FO cable, including FO pulling in existing duct, passing ARAMCO pipes at various locations. Used existing Manholes, Hand holes, with splicing, testing and commissioning.](_Image/scope.png) |